Stormwater Pipeline, Auckland

Project Description
Drill 20 x 18m deep piles and place universal columns and backfill with sand for top down construction of vertical access shaft for installing new stormwater pipeline

Machine used
CM39

Special difficulties
Traffic management and assisting with silt control was required.Piling was a continuous operation as weak ground conditions posed a potential problem